Anticipated WP3 Timeline

4th Quarter

STONE INSTALLATION 

  • Zone 1 Roof Commences
  • Apartment Fit Out Continues
  • Zone 1 Basement Front of House Areas Handed Over/Complete
  • Car Lift Install Continues (1 out of 2 complete)
  • Back of House Areas ongoing

1st Quarter

FRONT OF HOUSE 

  • Zone 1 Roof Continues
  • Zone 2 Roof Commences
  • Apartment Fit Out Continues
  • All Front of House Areas Handed Over/Complete
  • Car Lift Install Continues
  • Back of House Areas ongoing
  • Private Swimming Pools in progress

2nd Quarter

PLANT ROOMS 

  • Zone 1 Roof Continues
  • Zone 2 Roof Continues
  • Apartment Fit Out Continues
  • Back of House Areas ongoing
  • Plant Rooms Complete

3rd Quarter

SWIMMING POOLS 

  • Zone 1 Roof Continues
  • Zone 2 Roof Continues
  • Apartment Fit Out Continues
  • Zone 1 Back of House Areas Complete
  • Communal & Private Swimming Pools Complete