Anticipated WP2 Timeline

3rd Quarter

RESIDENTIAL FITOUT 

  • Stone facade installation commences (North party wall)
  • UKPN fitout commences
  • Residential fitout works commence
  • Core 1 slipform & precast stairs complete
  • South elevation repairs commence (3SAS)

4th Quarter

POWER AVAILABLE 

  • Tower crane 1 removed
  • Crystal & Garden gallery superstructure complete
  • Zone 1 substructure complete
  • Power available (LV switch room)
  • Lift installation commences

1st Quarter

ZONE 2 EXTERNAL SCAFFOLD 

  • Zone 2 substructure slabs poured
  • Zone 2 external scaffold commences
  • Front of House fitout commences
  • Crystal Gallery glazed roofing and facade commence

2nd Quarter

CRYSTAL GALLERY FITOUT 

  • Car lift works commence
  • Crystal Gallery fitout commences
  • Zone 2 private pools commence