Anticipated WP2 Timeline

3rd Quarter

SCAFFOLD INSTALLATION 

  • Commence excavation down to the final basement level B5 in the open area of Zone 2
  • Commence raft slab construction at level B5 in Zone 2
  • Jumpform core construction commences in Zone 2 along with superstructure works
  • Ongoing excavation works to the basement B5 level in the top-down area of Zone 1
  • Above ground superstructure works will continue in Zone 1 to the West of the site
  • Structural frame system and scaffold installation commences on the lower ground floor of South Audley Street and Hill Street

4th Quarter

WINDOW/STONE INSTALL 

  • Screed, Waterproofing and Scaffold Works Commence South Audley Street
  • Commencement of Façade System Installation
  • Installation of first windows
  • Level 5 handed over

1st Quarter

ROOFING/TERRACE WORKS 

  • Zone 1 Top-out
  • Roofing Works and Terrace Works Commence Zone 1
  • Internal Shell & Core Trades Commence Zone 1
  • Residential Fitout Package Commences

2nd Quarter

LIFT WORKS COMMENCE 

  • Basements Constructed (Zone 1 and 2);
  • Courtyard Handover to Follow on Trades;
  • Lift Works Commence
  • Zone 1 water

3rd Quarter

ENVELOPE COMMENCE ZONE 2 

  • Zone 2 Superstructure Complete
  • Envelope Commence Zone 2
  • Front of House White Box Works Commence