Anticipated WP2 Timeline

2nd Quarter

ZONE 1 SUPERSTRUCTURE 

  • First windows installed
  • Zone 1 superstructure complete
  • North party wall scaffold erection commences
  • Private pool shell works commence
  • South Audley Street facade ongoing

3rd Quarter

STONE FACADE 

  • Lift installation works commence
  • Stone facade installation commences (north party wall)
  • Tower crane 1 removal
  • UKPN fitout commences
  • Crystal & garden gallery superstructure complete

4th Quarter

RESIDENTIAL FIT OUT WORKS 

  • Residential fit-out works commence
  • Zone 1 substructure complete
  • Power available (LV switch room)
  • Core 1 slipform & precast stairs complete
  • Zone 2 substructure slabs poured

1st Quarter

COMMUNAL POOL WORKS 

  • Communal pool works commence
  • Waverton motor court build up complete
  • Car lift hoist 6 mobilised
  • Zone 2 external scaffold commences