Anticipated WP2 Timeline

4th Quarter

TOP OUT 

  • Waverton motor court first phase build complete
  • Zone 2 superstructure top out
  • Zone 1 stone facade installed to roof
  • Crystal Gallery envelope commences
  • First car lift installed
  • Zone 2 stone commencing

1st Quarter

WELFARE ACCOMODATION 

  • Zone 1 stone facade installed to roof
  • Crystal Gallery envelope commences
  • First car lift installed
  • Zone 2 stone commencing
  • Commence apartment fit-out

2nd Quarter

FRONT OF HOUSE 

  • Zone 1 roofing works complete
  • Pool works complete Zone 1 (WP3 works)
  • Welfare accommodation removed
  • Spa fit-out commences
  • Crystal Gallery fit-out commences
  • Passenger lift installation complete

3rd Quarter

POWER ON 

  • Permanent power to Zone 1
  • Zone 2 weathertight up to level 5