Anticipated WP2 Timeline

3rd Quarter

TOP OUT 

  • Townhouse 2&1 fit-out commences
  • Zone 2 courtyard structure poured
  • Front of house fit-out commences
  • Waverton Street drainage connections complete
  • Zone 2 scaffold erection commences
  • Zone 2 window installation commences

4th Quarter

SCAFFOLD REMOVED 

  • Waverton motor court first phase build complete
  • Zone 2 superstructure top out
  • Zone 1 stone facade installed to roof
  • Crystal Gallery envelope commences
  • First car lift installed
  • Zone 2 stone commencing

1st Quarter

WELFARE ACCOMODATION 

  • Zone 1 scaffold removed
  • Zone 1 roofing works complete
  • B3 plant spaces physically compete
  • Pool works complete Zone 1 (WP3 works)
  • Welfare accommodation removed

2nd Quarter

FRONT OF HOUSE 

  • Spa fit-out commences
  • Crystal Gallery fit-out commences
  • Passenger lift installation complete