Anticipated WP2 Timeline

4th Quarter

SCAFFOLD INSTALLATION 

  • Screed, Waterproofing and Scaffold works commence South Audley Street
  • Ongoing excavation works to basement B5 level in the top-down area of Zone 1
  • Zone 1 superstructure works ongoing
  • Commence raft slab construction at level B5 in Zone 2

 

1st Quarter

ZONE 1 SUPERSTRUCTURE 

  • South Audley St & Courtyard Façade works commence
  • Hoist 4 installation along South Audley Street
  • First windows installed in Zone 1
  • Zone 1 superstructure complete
  • Zone 2 substructure works ongoing

2nd Quarter

ZONE 1 FACADE 

  • Zone 1 substructure complete
  • Zone 1 Lift works commence
  • Zone 1 Stone install commences
  • Zone 1 North Party Wall scaffold erection
  • Zone 2 Basements constructed & superstructure underway
  • Zone 2 Jumpform core construction complete
  • Tower Crane 1 demobilised

3rd Quarter

ZONE 2 STRUCTURE COMPLETE 

  • Zone 2 Superstructure Complete
  • Scaffolding commences across Zone 2 elevations (Waverton/Hill St & Courtyard)
  • Façade works commence in Zone 2
  • Zone 2 Car Lift core complete & Material Hoist 6 installed

4th Quarter

ZONE 2 FACADE 

  • Tower Crane 2 relocated to Zone 2 Core 1
  • Hoists installed along Waverton/Hill St & Courtyard
  • Zone 1 stone installed up to L6
  • Zone 1 early shell & core commissioning activities commence
  • Zone 2 facade works underway