Anticipated WP2 Timeline

2nd Quarter

TOWNHOUSES 

  • Townhouse 2&1 fitout commences
  • Zone 2 courtyard structure poured
  • Waverton motor court first phase build complete
  • Front of house fitout commences
  • Waverton Street drainage connections complete
  • Zone 2 scaffold erection commences

3rd Quarter

ZONE 2 TOP OUT 

  • Zone 2 superstructure top out
  • Zone 1 stone facade installed to roof
  • Zone 2 window installation commences
  • Crystal Gallery envelope commences

4th Quarter

SCAFFOLD REMOVED 

  • Zone 1 scaffold removed
  • Zone 1 roofing works complete
  • B3 plant spaces physically complete
  • Pool works complete Zone 1 (WP3 works)
  • Zone 2 stone commencing
  • First car lift installed

1st Quarter

WELFARE ACCOMODATION 

  • Spa fit-out commences
  • Crystal Gallery fit-out commences
  • Passenger lift installation complete
  • Welfare accommodation removed