Anticipated WP2 Timeline

2nd Quarter

SUPERSTRUCTURE WORKS 

  • Ongoing construction of the superstructure slab works in Zone 1 to the West of the site
  • Basement slab construction continues at the top-down area of Zone 1
  • Commence excavation down to the basement level B4 in the open area of Zone 2
  • Temporary steel propping installation to perimeter basement at the B4 level
  • New welfare accommodation installation starts

3rd Quarter

SCAFFOLD INSTALLATION 

  • Commence excavation down to the final basement level B5 in the open area of Zone 2
  • Commence raft slab construction at level B5 in Zone 2
  • Jumpform core construction commences in Zone 2 along with superstructure works
  • Ongoing excavation works to the basement B5 level in the top-down area of Zone 1
  • Above ground superstructure works will continue in Zone 1 to the West of the site
  • Structural frame system and scaffold installation commences on the lower ground floor of South Audley Street and Hill Street

4th Quarter

WINDOW/STONE INSTALL 

  • Structural frame system and scaffold installation ongoing
  • Window and stone installation commences

1st Quarter

WINDOW/STONE ONGOING 

  • Structural frame system and scaffold installation ongoing
  • Window and stone installation ongoing

2nd Quarter

FACADE 

  • Hand Laid facade works start
  • Zone 2 basement complete